Daftar SPK Produksi Workshop
Monitoring Surat Perintah Kerja (PO Produksi), jadwal workshop, dan progres 8 tahapan pengerjaan.
| No. SPK / PO | Project & Klien | Kepala Produksi | Tahapan Saat Ini | Akumulasi Progress | Deadline Workshop | Status | Aksi |
|---|---|---|---|---|---|---|---|
| PROD-2026-001 |
Booth PT ABC – 6x6 Meter JCC
PT ABC INDONESIA
|
Andi Wijaya | ASSEMBLY & HPL |
52%
|
12 Sep | IN_PROGRESS | Update |
| PROD-2026-002 |
Booth PT XYZ – 3x3 Meter ICE
PT XYZ CREATIVE AGENCY
|
Andi Wijaya | HPL & FINISHING |
55%
|
14 Sep | IN_PROGRESS | Update |
| PROD-2026-005 |
Special Booth Sinar Oto JCC
PT SINAR OTOMOTIF JAYA
|
Bambang Irawan | FINAL QC TOUCH UP |
90%
|
05 Sep | QC_CHECK | Update |