PDO Off (Demo Active)

SURAT PERINTAH KERJA (SPK PRODUKSI)

IN PROGRESS

No PO: PROD-2026-001 | Project: Booth PT ABC – 6x6 Meter | Client: PT ABC INDONESIA

Kepala Produksi (PIC): Andi Wijaya
Target Deadline Workshop: 12 Sept 2026
Venue Pelaksanaan: JCC Senayan Hall A
Overall Progress: 52%
Total Akumulasi Progres Produksi 52% Selesai

KONTROL PROGRESS 8 TAHAPAN PRODUKSI WORKSHOP

Geser slider atau checklist untuk mengupdate progres per divisi workshop.

Bobot Terhitung: 100%
DESIGN Bobot: 10%
100% SELESAI
MATERIAL Bobot: 15%
100% SELESAI
CUTTING Bobot: 15%
75% PROSES
ASSEMBLY Bobot: 20%
50% PROSES
HPL Bobot: 15%
30% PROSES
PAINTING Bobot: 10%
0% PENDING
ELECTRICAL Bobot: 10%
0% PENDING
QC Bobot: 5%
0% PENDING

CHECKLIST QUALITY CONTROL (QC) WORKSHOP